Utilities & Energy Services – 2024 Summer Projects
Projected UES electrical, water, steam, storm, sanitary, and energy conservation projects this summer.
Links
Documents
Electrical Projects
• Activities & Recreation Center – Transformer Fan and Controller Upgrade Davenport Hall – Electrical Service Installation
• CABBI Fire Alarm System Installation
• DC-4 Replacement (ongoing preliminary work)
• Housing Food Stores – Electrical Service Upgrade (duct bank and cable work only)
• LC-21 Replacement
• Literatures, Cultures and Linguistics Building – Transformer Replacement
• McKinley Health Center – Fire Pump Controller Replacement
• Steven S. Wymer Hall – Electrical Service Installation
• University Press Building – Electrical Service Upgrade (duct bank and cable work only)
• Upgrade Fire Alarm Panel at 1114 Stoughton
Water Projects
• Replace Multiple Campus Fire Hydrants
• Remove the Fire Hydrant at First Street and Windsor Road
• 8” Water Main Work on the West Side of Sixth Street and South of John Street (near the Swanlund Administration Building)
• Valve Replacements: Southeast of Kenny Gym on Springfield Avenue and Southeast of the Krannert Art Museum
• Fourth Street Water Distribution Main Extension
• Transportation parking lot 6” main disconnect and abandon in place, connect Node #1 to 12” main, and hydrant #14 replace/relocate to 12” main
• 6” water main disconnect and abandon in place in grass field between PPSB and Memorial Stadium
• First Street and Gregory Drive Water Leak Repair
Steam Projects
• Scott Hall – Small Section Steam System Replacement
• Taft Van Doren Hall – Steam System Replacement
• Mathews Street – Shallow Tunnel PEX Installation/Condensate Piping
• Gregory Place – Steam System Replacement Vault-to-Vault
Storm/Sanitary Projects
• Harker Hall – Storm System Improvement
• Storm Manhole Replacement on Lincoln Avenue (North Side of Lincoln Avenue Residence Halls)
• Sanitary manhole replacement Document Services and Gregory Drive in the grass area
Energy Performance Contracting Projects
• EPC 005 – Complete warranty items and move to Final Acceptance July 2024 (Beckman, Roger Adams Laboratory, Illinois Sustainable Technology Center, NRSA)
• EPC 006 – Construction in progress and move to Substantial Completion (Oak Street Chiller Plant)Retrocommissioning
Retrocommissioning
• Illinois Conference Center Controls Upgrade